Due to national manufacturing and shipping delays, new electrical services requiring a padmount transformer (underground services) could be delayed until Spring 2023. Although the PUD ordered these a year ago, shipment continues to be delayed.

At a national level, public power representatives are requesting funding to bolster production of distribution transformers to combat the low supply.

Other materials for overhead service and other work orders may be currently available but are in an unpredictable market, where prices and delivery estimations are increasing.

Please contact your local PUD office and ask for a distribution engineer if you need more information about your new or upgraded electrical service. We thank you for your patience and understanding!

More News Articles

Okanogan County PUD was one of three public power utilities in the Pacific Northwest that were notified recently that they are eligible to receive…

When the Washington DNR contacted a local ISP for broadband service at their Salmon Fire command Center, the response was immediate.…

Okanogan County Community Action Council, through its Low Income Home Energy Assistance Program (LIHEAP), still has some funds left for the 2010-…

PUD No. 1 of Okanogan County General Manager John Grubich has submitted a letter to Omak Chronicle Editor Roger Harnack in response to an…

We are now offering online billing and payment service. This service is limited to the ability to receive and pay your Okanogan PUD electricity…