Due to national manufacturing and shipping delays, new electrical services requiring a padmount transformer (underground services) could be delayed until Spring 2023. Although the PUD ordered these a year ago, shipment continues to be delayed.

At a national level, public power representatives are requesting funding to bolster production of distribution transformers to combat the low supply.

Other materials for overhead service and other work orders may be currently available but are in an unpredictable market, where prices and delivery estimations are increasing.

Please contact your local PUD office and ask for a distribution engineer if you need more information about your new or upgraded electrical service. We thank you for your patience and understanding!

More News Articles

Okanogan PUD employee, Debbie Peters, was on hand at the Northwest Public Power Association’s (NWPPA) Excellence in Communications event in…

Yesterday, the PUD sent out a press release regarding fire in the Grand Coulee area damaging and threatening several BPA transmission lines.…

Fires in the area have taken out two BPA transmission lines serving the Okanogan County PUD.  A third BPA transmission line serving Okanogan…

Okanogan County Fair 2012 Employee Volunteers - the Key to Success!

Once again, the Okanogan PUD's presence at the…

Okanogan PUD just completed its North American Electric Reliability Corporation/ Western Electricity Coordinating Council Compliance Audit. The…

July 5, 2012 was payday for Okanogan County PUD’s twenty-five producers who generate renewable solar or wind energy and who participate in our…