Due to national manufacturing and shipping delays, new electrical services requiring a padmount transformer (underground services) could be delayed until Spring 2023. Although the PUD ordered these a year ago, shipment continues to be delayed.

At a national level, public power representatives are requesting funding to bolster production of distribution transformers to combat the low supply.

Other materials for overhead service and other work orders may be currently available but are in an unpredictable market, where prices and delivery estimations are increasing.

Please contact your local PUD office and ask for a distribution engineer if you need more information about your new or upgraded electrical service. We thank you for your patience and understanding!

More News Articles

During 2015 Okanogan PUD anticipates bidding 15kV distribution line work related to the Carlton Complex Fire, energized and de-energized…

There will be a Special Meeting of the Board of Commissioners of Public Utility District No. 1 of Okanogan County on Monday, March 9, 2015…

February 4, 2015

Please be on alert for another scam targeting PUD customers in Okanogan County.

This latest threat comes from…

Draft Resolutions authorizing the Commissioning or De-Commissioning of Enloe Dam were introduced at the January 26, 2015 Board meeting. The Board…

January 29, 2015

Today the Washington Supreme Court confirmed the PUD's statutory authority to acquire necessary right-of way for the…

January 16, 2015

Recently the PUD has been notified by residential and commercial customers in the Oroville area that they have been…