Due to national manufacturing and shipping delays, new electrical services requiring a padmount transformer (underground services) could be delayed until Spring 2023. Although the PUD ordered these a year ago, shipment continues to be delayed.

At a national level, public power representatives are requesting funding to bolster production of distribution transformers to combat the low supply.

Other materials for overhead service and other work orders may be currently available but are in an unpredictable market, where prices and delivery estimations are increasing.

Please contact your local PUD office and ask for a distribution engineer if you need more information about your new or upgraded electrical service. We thank you for your patience and understanding!

More News Articles

The Board of Commissioners has been provided a copy of the 2016 Proposed Budget and the District's budget hearing was opened at its regularly…

Due to there being no items appropriate for executive session as allowed in the Open Public Meetings Act, the President of the Board of…

October 4-10, 2015 is Public Power Week, a time when communities across the U.S. celebrate the advantages of public power. More than 2,000 cities…

The Bonneville Power Administration (BPA) is increasing the cost of power it sells to Okanogan PUD by approximately $1…

Please join the Okanogan PUD this Saturday, October 3, 2015 in the main PUD parking lot in Okanogan, 10:00 am - 3:00…

The Regular Meeting of the Board of Commissioners of Public Utility District No. 1 of Okanogan County scheduled on September 28, 2015 at 2:30 p.m…