Due to national manufacturing and shipping delays, new electrical services requiring a padmount transformer (underground services) could be delayed until Spring 2023. Although the PUD ordered these a year ago, shipment continues to be delayed.

At a national level, public power representatives are requesting funding to bolster production of distribution transformers to combat the low supply.

Other materials for overhead service and other work orders may be currently available but are in an unpredictable market, where prices and delivery estimations are increasing.

Please contact your local PUD office and ask for a distribution engineer if you need more information about your new or upgraded electrical service. We thank you for your patience and understanding!

More News Articles

The Board of Commissioners of Public Utility District No. 1 of Okanogan County will be holding a special meeting Monday, March 2, 2020, from 6-8 p.m…

Okanogan County PUD commissioners continued their discussions regarding rates and costs at their Feb. 24 meeting, presenting proposed rate changes…

To cut expenses, the Okanogan County PUD will make changes to its Omak office location, beginning March 1.

As of March 1, the office…

Okanogan County PUD commissioners continue to discuss setting rates to meet the 2020 budget, which was approved with a 2 percent revenue increase…

The Board of Commissioners of Public Utility District No. 1 of Okanogan County will be attending the February 12-14, 2020 meetings of the Washington…

The Okanogan County PUD commissioners recognized the combined 55 years of service of three employees at the Jan. 27 board meeting.