Due to national manufacturing and shipping delays, new electrical services requiring a padmount transformer (underground services) could be delayed until Spring 2023. Although the PUD ordered these a year ago, shipment continues to be delayed.

At a national level, public power representatives are requesting funding to bolster production of distribution transformers to combat the low supply.

Other materials for overhead service and other work orders may be currently available but are in an unpredictable market, where prices and delivery estimations are increasing.

Please contact your local PUD office and ask for a distribution engineer if you need more information about your new or upgraded electrical service. We thank you for your patience and understanding!

More News Articles

As Okanogan County PUD continues its plan for critical infrastructure upgrades, the board has approved a 3.25% overall revenue increase effective…

The Board of Commissioners of Public Utility District No. 1 of Okanogan County will be holding a virtual workshop Monday, February 22, 2021, at 2:00…

The Okanogan County PUD continued the discussion Feb. 8 regarding adjusting rate structures to move closer to actual costs of providing services…

Okanogan County PUD continues to work toward infrastructure repairs and upgrades, this time receiving five bids for steel poles to replace the…

With continuing COVID-19 cases in our Okanogan building, we are keeping the office closed this week and minimizing any staff in the building as…

As part of their ongoing plans to upgrade infrastructure, Okanogan County PUD commissioners approved a $2.4 million bid for six substation power…