The Okanogan County PUD commissioners approved the 2019 budget at their Dec. 17 meeting, calling for $55.7 million in revenue, $49.6 million in expenditures and $3.7 million in debt service.

The budget also includes bonding additional money to cover the costs of upgrading and replacing aging infrastructure to improve reliability and better serve customers. The budget anticipates $19.6 million in capital outlay, including design and construction at the Tonasket substation and the Okanogan-Brewster transmission line.

With the additional expenses incurred, the utility expects to increase revenue by 1.5 percent by raising the base charge next year. However, a separate resolution will need to be passed by commissioners before a rate increase goes into effect. General Manager Steve Taylor said a rate study will be done in the coming year, looking out 10 years to plan for needs ahead.

The budget was adopted after several months of budget hearings and special meetings.

Read more about the 2019 Budget Here.

In other business, the board:

- Approved Resolution 1676 to lower some wholesale broadband rates. The changes only affect carriers and large business customers, and make the rates more competitive in the market. Power Resource Manager Ron Gadeberg said he expects some of these customers will upgrade their services based on the new rates, and the District will be more attractive to new customers.

- Approved Resolution 1678, changing the board meeting schedule to remove the 2:30 p.m. regular executive session. Instead, if an executive session is needed, it will be called as needed during the regular meeting, or a special meeting will be called.

- Approved Resolution 1679, formally authorizing the general manager to approve leave or incentive programs in special circumstances. Examples would be in inclement weather, allowing employees to leave work early, or an employee receiving a service award at a milestone mark.

- Approved a contract with Christensen Associates, not to exceed $253,000, for dam safety work at Enloe Dam in 2019.

- Heard that Taylor signed a land-use agreement with BPA, which will allow Okanogan PUD to build a direct line from the Twisp substation to the existing Winthrop tap. This will create redundancy for Winthrop, through the Pateros-to-Twisp transmission line and the Loup.

More News Articles

The Board of Commissioners of Public Utility District No. 1 of Okanogan County will be holding a special meeting Monday, September 21, 2020, @ 3:00 p…

While some areas are still smoldering in Okanogan County, the PUD line crews have restored power to those customers who can be restored, and will…

Okanogan County PUD commissioners decided to tap into the rate stabilization fund to cover $622,455 in revenue shortfall after canceling the 2020…

Any K-5 children in the PUD service area are invited to enter a coloring contest to win prizes! The print newsletter has now gone out to all…

Okanogan County PUD crews are working on their plan to restore services throughout the area, but need customer feedback to help shape that plan.…

Financial Workshop Teleconference Availability Only: Phone: 1-346-248-7799 Meeting ID: 922 7822 8992 There will be a special meeting of…